Application
|
 |
 |
Lay the paving onto the base according to the manufacturers instructions for use. Allow a minimum joint width of 5 – 6mm and a depth of at least 25mm. Steps should be secured by mortar.
|
|
 |
 |
Cut the special vacuum pack. Empty GEO-fix® Jointing Compound onto the paving (sufficient to cover 4 – 5 m2) |
|
 |
 |
Simply brush the GEO-fix® Jointing Compound into the joints, moving the excess onto the next area to be filled. |
|
 |
 |
GEO-fix® Jointing Compound can be compacted into the joints with a pointing tool , trowel or with a mechanical vibrating machine |
|
 |
 |
Once cured, any residue can be easily removed from the paving by brushing with a stiff brush. |
|
|